Middle School
Type of Work
: Renovation and New Construction

Total Area
: 193,170 sq ft

Date Completed
: August 2006
 
Project Overview:
 
Norwin Middle School was the fourth major project in the overall district improvements.  The existing building underwent a thorough renovation including a state of the art auditorium, technical upgrades and ADA compliance.  The expansion included the addition of:
  • a new wing containing a band room, orchestra room. music classroom, three practice rooms, and an instrument storage room.
  • building addition also included two Art classrooms and two Family and Consumer Science classrooms, two computer labs, and additional classrooms.
  • revision to the existing access road and parking area.
  • paved student access to the stadium complex.
  • new softball and soccer fields.